Projects/Christy Drive Bridge — Port Kembla

Case Study

Christy Drive Bridge — Port Kembla

D&C delivery of an 18 m single-span SM1600 bridge to TfNSW specifications — industrial access at Port Kembla NSW.

Christy Drive Bridge — Port Kembla
Civil EngineeringPort Kembla, NSW2025–2026Industrial client — TfNSW specification

Project period · 2025–2026

Design and construct delivery of an 18 m single-span SM1600 bridge to TfNSW specifications — industrial access at Port Kembla NSW.

Project Context

Christy Drive at Port Kembla required a new industrial access bridge to carry SM1600 traffic loads into a working port and steelworks environment, delivered under a design-and-construct model with TfNSW compliance.

Engineering Scope

  • Safety in Design of removal of existing bridge and construction of new bridge
  • Design review of demolition methodology and drawings of existing damaged bridge
  • Civil and structural design review of 18 m single-span bridge superstructure and supports on behalf of the client (BlueScope Steel)
  • Alignment, pavement interfaces and drainage tie-ins review and amendments
  • Design to TfNSW bridge design requirements and relevant AS/NZS standards
  • Durability detailing for marine-influenced exposure classification
  • Design and temporary design review, as-built documentation and D&C coordination
  • Constructability review with contractor on erection sequence and temporary works

Outcomes

  • Compliant industrial bridge for Port Kembla access
  • Efficient D&C delivery with integrated civil/structural documentation
  • Durable details appropriate for coastal industrial service life

Engineering capabilities applied